Harris County set the flood control rate at exactly the voter-approval line. Its own budget says 25 of 181 bond projects are paused.

Harris County adopted a flood control tax rate of 5.266 cents per $100, which is exactly the voter-approval rate, the most the district can levy without an election. The county’s own adopted budget says 25 of the 181 project groups in the 2018 flood bond program are paused. It does not say which ones, or what paused means.

Why it matters

The flood district is the smallest line on your county tax bill and the one with the clearest promise attached to it. Residents approved $2.5 billion in 2018 to stop flooding. Eight years later the county is collecting more and has $1.39 billion of that authority still unissued.

By the numbers

  • The adopted FY27 flood control rate is 5.266 cents per $100, up from 4.966 cents. That is a 6.04 percent rate increase.
  • The adopted rate equals the voter-approval rate to the hundred-thousandth. The no-new-revenue rate is 4.955 cents, so the adopted rate sits 6.28 percent above it.
  • The district expects $266.2 million in FY27, against $251.1 million in FY26, about $15 million more.
  • The budget’s own cover page says it raises $21,613,712 more from property taxes than last year, a 6.4 percent increase, of which $6,859,140 comes from new property.
  • Of the 181 Bond IDs in the 2018 program: 58 completed, 15 closing, 11 transferred, 25 paused, 72 active, as of June 2026.
  • Of the $2.5 billion authorized in 2018, $1,109,645,000 has been issued and $1,390,355,000 has not, as of June 30, 2026.
  • Flood control debt secured by property taxes totals $1,025,020,000. FY27 payments on the flood bonds are $79.1 million.
  • The district’s maintenance and operations rate was 2.043 cents in 2022 and is 4.023 cents now, a 97 percent increase in four years.

On a home with $300,000 in taxable value, the flood line is about $158 a year, and the increase is about $9. That is our arithmetic on the adopted rate, not a district figure.

What the coverage buried

Community Impact’s account of the budget vote correctly names all four taxing units Commissioners Court sets, including the Flood Control District, and reports the 7.6 percent headline increase. It prints none of the four rates. A reader cannot tell from it that the flood district’s rate was set at its ceiling, because the ceiling is not in the story and neither is the rate. The figures are on the second page of the county’s own adopted budget.

The other side

The district has a real case and the budget book makes it. Voters approved the higher maintenance rate in November 2024. The county says the money moves the system from an estimated 270-year rehabilitation and replacement cycle to a 67-year one, which is a maintenance argument, not a wish list. And a paused project is not always a failed project. Sequencing 181 project groups across 23 watersheds means some wait.

The answer is that the document asking for the money will not define its own term. “Paused” is the budget book’s label, used without a definition and without naming one of the 25. Eight years in, more than half the bond authority is still unissued. A resident whose project is among the 25 cannot learn that from the budget, and the rate went to the ceiling either way.

What to watch

  • October 15, 9 a.m., 1001 Preston: the only regular Commissioners Court meeting before the election. No agenda was posted as of October 3.
  • Whether the Flood Control District publishes the list of the 25 paused Bond IDs and a definition of paused.
  • The $87 million the budget describes as the only unallocated reserve left in the 2018 program.
  • Whether the unissued $1.39 billion moves in FY27, and at what interest cost.

Bottom line

The flood district took the highest rate it could take without asking voters again, and the budget that justifies it reports 25 paused project groups without identifying one of them. The rate is public to five decimal places. The project list is not.