The Ship Channel bridge was due in 2024. Half of it opens in spring 2027, the rest by the end of 2030.

The Ship Channel bridge was due in 2024. Precinct 2 Commissioner Adrian Garcia announced this week that the south lanes open in spring 2027 and the north side by the end of 2030. The original contract was $962 million. The project now runs $1.45 billion.

Why it matters

The Dr. Richard A. Tapia Bridge is paid for out of Harris County Toll Road Authority revenue, which means the people paying are the people driving. Every year of delay is another year of about 55,000 vehicles a day crossing a 1982 span with four lanes and no breakdown shoulders.

By the numbers

  • $962 million: the original contract. $1.45 billion: the figure in this week’s coverage. The difference is $488 million, about 51 percent over.
  • March 2018: construction began. Spring 2027 for the south lanes is nine years later. End of 2030 for the north side is nearly thirteen.
  • 2024: the completion date FOX 26 reported in December 2021. Into 2028: the target HCTRA and its contractors gave after the redesign. End of 2030: the date now.
  • 21: significant design defects an independent engineering consultant found in the cable-stayed plans.
  • $291 million: the December 2021 contract amendment to demolish and rebuild the pylons.
  • $24.9 million: paid to COWI North America, hired October 2020 after FIGG Bridge Engineers was terminated in August 2020.
  • 514 feet tall, four 12-foot lanes each way. Traffic is projected to reach 160,000 vehicles a day.

What the coverage buried

The framing on this round is that the bridge finally has a timeline. The number that would tell you what the timeline is worth is not in it.

In December 2021, when HCTRA explained the $291 million fix, its executive director said the work would run into 2028. Construction Equipment Guide reported the contractors targeting early 2028 three months later. The date announced this week for the north half is the end of 2030. So this is not a schedule being met. It is a schedule slipping about three more years, on top of the six-year slip from the original 2024 date, and no accessible account of Garcia’s announcement puts the new date next to the old one.

The second gap is the money already spent. In December 2021 the county said it was examining how to recover the design fee paid to FIGG, which the Federal Highway Administration had suspended. Five years on, the current coverage does not say where that recovery stands or whether a dollar came back.

The other side

The strongest case for the county is that stopping was correct. An outside engineering review found pylons that could not carry the load they were designed for. Roberto Trevino, then HCTRA’s executive director, said the structure “could have collapsed.” Nobody should want the fast, cheap version of a 514-foot bridge over the Houston Ship Channel, and this is toll funded, not a property tax overrun.

Concede all of it. The safety call was right, and it was made by the agency that had the most to lose from making it. What that does not answer is the two and a half years of building that came first. The county selected the designer, approved the plans and poured concrete until an outside reviewer counted 21 defects. The demolition was the correct response to a failure of oversight, not a substitute for explaining it.

What to watch

  • Spring 2027, the south lanes opening, the first date anyone can be held to.
  • HCTRA board agendas for any further contract amendment on the north side before 2030.
  • Whether Commissioners Court ever reports a recovery from FIGG or its insurers.
  • HCTRA toll revenue and its transfers in the fiscal 2027 county budget, which is where the cost of the extra years shows up.

Bottom line

A firm date on half a bridge is real progress after eight years, and it deserves to be reported as such. It is also the third schedule this project has had, each one announced with confidence. The number worth tracking is not the opening date. It is whether the county ever recovered anything from the design that cost $488 million and six years to correct.